Construction Schedule: Twelve weeks
Project: DSTL HS Area
Services: Electrical
Client: Serco
Contract Value: £200k
We took on the role of principal contractor for this project to design and install the electrical upgrade of existing buildings at the HS site at Porton Down and for the new electrical installation of refurbished buildings.
Our engineers had to be CompEx certified to work within certain areas and have a good understanding of the requirement. The project had to be turned around very quickly from tender, acceptance, design, project commencement, commissioning and handover.