CEAL PROJECT – DSTL Porton Down

Construction Schedule: Six months
Project: CEAL Project
Services: Mechanical, Electrical, BMS
Client: Serco
Contract Value: £500k

Description

Our role in this project was to act as principal contractor for the client, managing the complete specialist laboratory refurbishment.

Detail

We completed the install of all associated electrical and mechanical equipment, including the specialist systems such as air conditioning and BMS controls. We also oversaw the building works and final decoration works, seeing the project through to final completion. We were awarded a seven star rating for our work on this refurbishment which is the highest possible rating on this site and we were the first contractor to achieve this.